Commercial Building Project, completed in Runcorn.
INTERNAL FIT-OUT
Work undertaken by Urban
Urban Building Projects were asked to build 7 offices, a meeting room, a staff canteen, changing quarters, toilets for ladies/gents, a full disability WC and changing facilities for Polyflex Packaging in Runcorn.
It was an empty warehouse where we built the offices internally. We built in blockwork and a timber framed flat roof which acted as a storage unit.
The project required us to:
fully finish the offices/toilets to a plastered finish
install a full electrical and AV system
install a full heating system
complete with a high standard of internal joinery finishes.
This project lasted 12 weeks from start to finish and we worked with Halton Council throughout the build. The work was completed on time and within the client's budget.